What is Power Usage Effectiveness (PUE) and how is it Calculated?

Posted on October 13, 2014 by Gento

Raritan PUE Power Usage Effectiveness Total Facility Power

The Power Usage Effectiveness (PUE) metric which was first introduced by The Green Grid™ in 2007 has become the de facto standard for measuring data center efficiency.  But despite its prevalence, many data center operators are unclear on what PUE is, how it is calculated, and how it can be used to further energy efficiency initiatives. For instance, many data center managers know that their PUE readings should be as close to the number one as possible, but why?

PUE is a ratio of the amount of power needed to operate and cool the data center vs. the amount of power drawn by the IT equipment in the data center.  The equation looks like this:

PUE = (Total Facility Energy) / (IT Equipment Energy)

Thus having a PUE of one would mean that you have a perfect data center where all the power coming into the building makes it to the IT equipment with none used for cooling systems or lighting, or lost in transmission to the IT equipment. 

So now that you understand the equation, you may be wondering how you can collect data for both facility and IT equipment.  For facility, most rely on a utility meter.  However, installing what is called a “shadow meter” allows data center operators to track total facility power utilization on a daily basis instead of waiting on the monthly utility bill.

For IT equipment, it is best to collect power data from your rack power distribution units (PDUs) as they can often meter down to the individual outlet level providing insights into the efficiency of individual equipment.  Other times you may be able to collect this information from remote power panels (RPPs) or uninterruptible power supplies (UPS).  And in the event that neither provides metering capabilities, you may consider adding an aftermarket branch circuit meter with split-core current transformers that snaps into existing panels.

The data you collect can be manually added to a worksheet at predetermined intervals and you can set up functions or macros to perform your calculations for you.  Or you can use intelligent rack PDUs that send data over the network to a database that is connected to a DCIM power monitoring solution that will automatically calculate PUE, reveal trends over time, and help data center managers to evaluate how well efficiency initiatives are performing.  

 

Learn more about how Raritan's data center energy management solution automatically calculates PUE or take our DCIM monitoring tool for a spin right from your computer. 


Take a Test Drive Now

Other Blog Posts

What Is a Neocloud—and Why It Matters for Modern Data Centers
Posted on June 1, 2026
Beyond Containment: How Advanced Sensing Is Changing Data Center Cooling
Posted on June 1, 2026
Universal Input: Delivering Seamless Plug-and-Play Flexibility in Data Centers with Universal Input
Posted on March 1, 2026
The Intelligent PDU: A Critical Component for Power Management in AI Data Centers
Posted on December 17, 2025
How Remote Medical Scanning Streamlines Operations and Improves Patient Satisfaction
Posted on November 24, 2025

View all Blog Posts

Subscribe

Upcoming Events

Japan Cloud & Datacenter Convention 2025
06 Jun 2025  •  Tokyo, Japan
Interop Tokyo 2025
11 Jun - 13 Jun 2025  •  Chiba, Japan
Suntelephone ICT Business Solution 2025 (Sendai)
17 Jun 2025  •  Sendai, Japan
Suntelephone ICT Business Solution 2025 (Kanazawa)
25 Jun 2025  •  Kanazawa, Japan
Suntelephone ICT Business Solution 2025 (Takamatsu)
04 Jul 2025  •  Takamatsu, Japan

View all Events

Latest News

Legrand Introduces Next-Generation KVM Platform Built to Bring Critical Systems Back Online in Minutes
Posted on October 22, 2026
Legrand Certifications and Process Controls Provide Confidence in Information Security for Network-Connected Devices in Data-Related Applications
Posted on July 1, 2024
Legrand Revitalizes Data Center Sector with Two Revolutionary Intelligent Rack PDUs
Posted on May 1, 2023
Exclusive interview丨How does Huizhou upgrade its manufacturing industry?
Posted on December 2, 2021
Raritan Reveals The MasterConsole® Digital Dual KVM Switch
Posted on February 18, 2021

View all news